1. Draw a network diagram for this project. Identify all the paths through the network diagram.
2. Simulate the completion of this project 1000 times assuming that activity times follow a triangular distribution. Estimate the mean and standard deviation of the project completion time.
3. Develop a histogram to summarize the results of your simulation.
4. Calculate the probability that the project can be completed within 30 months. What is the probability that the project will take longer than 40 months? What is the probability that the project will take between 30 and 40 months?
NutriStar produces a line of vitamins and nutritional supplements. It recently introduced its Nutri-Sports Energy Bar, which is based on new scientific findings about the proper balance of macronutrients. The energy bar has become extremely popular among elite athletes and other people who follow the diet. One distinguishing feature of the Nutri-Sports Energy Bar is that each bar contains 50 milligrams of eicosapentaenoic acid (EPA), a substance strongly linked to reducing the risk of cancer but found in only a few foods, such as salmon. NutriStar was able to include EPA in its sports bars because it had previously developed and patented a process to refine EPA for its line of fish-oil capsules. Because of the success of the Nutri-Sports Energy Bar in the United States, NutriStar is considering offering it in Latin America. With its domestic facility currently operating at capacity, the President of NutriStar has decided to investigate the option of adding approximately 10,000 square feet of production space to its facility in Latin America at a cost of $5 million.
SOLUTION
1.
The following abbreviations will be used for the activities.
| Activity Description | Abbreviation |
|---|---|
| Concept Development | A |
| Plan Development | |
| Define project scope | B |
| Develop broad schedule | C |
| Detailed cost estimates | D |
| Develop staffing plan | E |
| Design and Construction | |
| Detailed engineering | F |
| Facility construction | G |
| Mobilization of construction Employees | H |
| Procurement of equipment | I |
| Start-up and Turnover | |
| Pre-startup inspection | J |
| Recruiting and training | K |
| Solving start-up problems | L |
| Centerlining | M |
Using these abbreviations and the information provided in the case, the following AOA network diagram can be constructed.
B F
G
A C H I J K
D
L M
E
There are 32 paths through the network as follows
A, B, F, G, J, K, M A, D, F, G, J, K, M
A, B, F, G, J, L, M A, D, F, G, J, L, M
A, B, F, I, J, K, M A, D, F, I, J, K, M
A, B, F, I, J, L, M A, D, F, I, J, L, M